Maylands Lakes
MAYLANDS LAKES PHASE ONE IMPLEMENTATION
At its April 2025 meeting, Council endorsed the Maylands Lakes Environmental Restoration Concept Report, with $2.4 million allocated to implement Phase 1 actions in the City's 2025/26 Budget. Updates to the Implementation timeline will be posted here as the project progresses.
To read more about Phase 1 activities please Click on the News Items below.
Masterplan implementation update
Landscape and Green Infrastructure assessment
ENVIRONMENTAL RESTORATION MASTERPLAN
The City of Bayswater is committed to improving the water quality at Maylands Lakes.
In April 2024, Council endorsed the preparation of a Maylands Lakes Environmental Restoration Masterplan to develop a solution to improve water quality, reduce midge and algal blooms, and enhance amenity and access to nature in the area. The Masterplan was endorsed by Council in April 2025, and an estimated implementation timeline presented to the community. An updated version of the implementation timeline is available to view.
WATER QUALITY AND MIDGE DATA
Dashboards are available below offering detailed information on water quality monitoring and midge management and will be updated to provide ongoing information. Find out more by clicking the relevant button below.
STAY UP TO DATE
Community forums are held to provide residents with updates on the Masterplan and other activities at Maylands Lakes. More information is available in the Frequently Asked Questions or check the News Feed below.
You can also register to follow this project at the top-right of this page.
MAYLANDS LAKES PHASE ONE IMPLEMENTATION
At its April 2025 meeting, Council endorsed the Maylands Lakes Environmental Restoration Concept Report, with $2.4 million allocated to implement Phase 1 actions in the City's 2025/26 Budget. Updates to the Implementation timeline will be posted here as the project progresses.
To read more about Phase 1 activities please Click on the News Items below.
Masterplan implementation update
Landscape and Green Infrastructure assessment
ENVIRONMENTAL RESTORATION MASTERPLAN
The City of Bayswater is committed to improving the water quality at Maylands Lakes.
In April 2024, Council endorsed the preparation of a Maylands Lakes Environmental Restoration Masterplan to develop a solution to improve water quality, reduce midge and algal blooms, and enhance amenity and access to nature in the area. The Masterplan was endorsed by Council in April 2025, and an estimated implementation timeline presented to the community. An updated version of the implementation timeline is available to view.
WATER QUALITY AND MIDGE DATA
Dashboards are available below offering detailed information on water quality monitoring and midge management and will be updated to provide ongoing information. Find out more by clicking the relevant button below.
STAY UP TO DATE
Community forums are held to provide residents with updates on the Masterplan and other activities at Maylands Lakes. More information is available in the Frequently Asked Questions or check the News Feed below.
You can also register to follow this project at the top-right of this page.
-
Latest news
Following Queensland COVID risk status being reduced to very low risk on 27th October 2021, the WEARS contractors who are supplying and installing the mechanical mixers have now been able to gain access to Western Australia. Final preparations are now being undertaken and a mixer will be installed in Lake Brearley and Lake Bungana this week.
The installation of the mixers is an important milestone in the delivery of the water quality improvement plan as they are designed to address the stratification (lack of mixing of cooler and warmer water) of the water within the lakes. The GHD monitoringContinue reading
Following Queensland COVID risk status being reduced to very low risk on 27th October 2021, the WEARS contractors who are supplying and installing the mechanical mixers have now been able to gain access to Western Australia. Final preparations are now being undertaken and a mixer will be installed in Lake Brearley and Lake Bungana this week.
The installation of the mixers is an important milestone in the delivery of the water quality improvement plan as they are designed to address the stratification (lack of mixing of cooler and warmer water) of the water within the lakes. The GHD monitoring report identified stratification as a key contributor to excess nutrient levels in the lakes. It is anticipated the mixers should reduce the stratification within approximately two months, which as part of the range of approved actions, should progressively improve the water quality in the lakes.
The City has signed a contract with Apex Envirocare to undertake dredging of Lake Brearley. Dredging is scheduled to commence on 29th November 2021. The dredge being used is significantly more powerful than the dredge used on Lake Bungana. City officers will work with Apex Envirocare to monitor the volume of sediment removed and the area of lake floor dredged.
City officers are continually monitoring emerging technology and innovative options to improve water quality and reduce midge at Maylands Lakes. Recently this has resulted in the City commencing a 12 month trial installation of ultrasonic units in Lake Brearley. The devices are solar powered and emit ultrasonic waves that cause gas pockets in algae cells to collapse resulting in the algae sinking and dying. There have been no reports of harm to humans, fish, birds and other fauna due to ultrasonics. The installation of the units is an additional action being taken by the City to complement the other initiatives that are already planned and being actioned.
The raingarden at Tourer Court is now complete and will reduce some of the nutrients flowing into Lake Brearley.
A focused regime of midge and mosquito treatment was undertaken this past summer and feedback and monitoring indicated midge levels were lower. The same treatment approach has commenced early this year in response to midge levels.
Clean fill has been placed into the corner of Lake Brearley adjacent to Sopwith Elbow and Tourer Court which suffers from reduced circulation and tends to collect the floating algae. Final levels of this fill will be achieved once the water level reduces – we are targeting fill level to be approximately at the low water mark. This area will be planted with sedges once the final fill levels are achieved.
The floating wetlands have been removed from Lake Brearley as they were not thriving and they have been relocated to Lake Bungana, Brickworks Lake and the pond at Bardon Park.
Approximately 40 sedges have been installed along the hard wall in the south eastern corner of Lake Brearley. Installation of plants in these locations is challenging as there is limited fill and primarily limestone rock. City officers are trialing a new installation technique to determine its effectiveness. If it is found to be effective, there are a further 300 sedges to be planted once the water levels reduce.
In addition to the above actions, the City continues to monitor the latest advances in technology and water management approaches to ensure the most appropriate and impactful actions are taken at Maylands Lakes.
-
Planting Days
Three successful planting days have been held this planting season:
- 30 May 2021 at Lake Brearley in partnership with Friends of Maylands Lakes
- 7th August 2021 at Brickworks Stream in conjunction with Friends of Maylands Lakes
- 15th August 2021 at Brickworks Reserve in conjunction with Friends of Maylands Brickworks.
It was great to see so many community members participate in the planting days with a total of approximately 5000 plants planted.
Three successful planting days have been held this planting season:
- 30 May 2021 at Lake Brearley in partnership with Friends of Maylands Lakes
- 7th August 2021 at Brickworks Stream in conjunction with Friends of Maylands Lakes
- 15th August 2021 at Brickworks Reserve in conjunction with Friends of Maylands Brickworks.
It was great to see so many community members participate in the planting days with a total of approximately 5000 plants planted.
Follow Project
Landscape and Environment Restoration Assessment
Landscape and Green Infrastructure Assessment Area Documents
-
Landscape assessment by area (x 15)
-
Maylands Lakes LGI Assessment Area 2 (5.49 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 4 (6.25 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 1 (5.08 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 3 (5.72 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 5 (4.85 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 6 (5.2 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 7 (4.78 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 8 (4.54 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 9 (5.16 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 10 (5.86 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 11 (5.92 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 12 (6.21 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 13c (2.97 MB) (pdf)
-
Maylands Lakes LGI Assessment Area 13a and b (3.81 MB) (pdf)
-
State & Federal Government Representatives
Documents
-
Maylands Lakes Phase One Implementation Updated Timeline- 30 April 2026 (73.6 KB) (pdf)
-
Maylands Lakes Phase One Implementation Timeline - 6 February 2026 (72.6 KB) (pdf)
-
Community Forum Documents
-
Forum Report Maylands Lakes Community Forum August 2025 (4.15 MB) (pdf)
-
Maylands Lakes Community Forum slides 28 August 2025 (4.19 MB) (pdf)
-
Forum Report Maylands Lakes Community Forum 15 May 2025 (1.21 MB) (pdf)
-
Maylands Lakes Community Forum slides 15 May 2025 (2.79 MB) (pdf)
-
Forum Report Maylands Lakes Community Forum December 2024 (1.97 MB) (docx)
-
Maylands Lakes Community Forum slides 12 December 2024 (1.87 MB) (pdf)
-
Forum Report Maylands Lakes Community Forum 5 September 2024 (592 KB) (pdf)
-
Maylands Lakes Community Forum slides 5 September 2024 (3.6 MB) (pdf)
-
Maylands Lakes Action List - 28 June 2024 (61 KB) (pdf)
-
Forum Report Maylands Lakes Community Forum 15 June 2024 (753 KB) (pdf)
-
Maylands Lakes Community Forum slides 15 June 2024 (5.19 MB) (pptx)
-
March 2021 - Maylands Lakes Community Information Session (23.8 MB) (pdf)
-
-
Scientific Advisory Panel (SAP) Documents
-
Maylands Lakes Scientific Advisory Panel meeting notes Dec2025_final.pdf (156 KB) (pdf)
-
Maylands Lakes Strategic Advisory Panel meeting notes Mar2025.pdf (145 KB) (pdf)
-
Maylands Lakes Scientific Advisory Panel meeting notes Jan2025_final for SAP.pdf (101 KB) (pdf)
-
Maylands Lakes Scientific Advisory Panel meeting notes Dec24_final.pdf (1.03 MB) (pdf)
-
Maylands Lakes Scientific Advisory Panel meeting notes Oct24_final.pdf (630 KB) (pdf)
-
Mar 2024 - Maylands Lakes Scientific Advisory Panel Workshop 2 notes (121 KB) (pdf)
-
Feb 2024 - Maylands Lakes Scientific Advisory Panel Workshop 1 notes (92 KB) (pdf)
-
Feb 2024 - Terms of Reference - Maylands Lakes Scientific Advisory Panel.pdf (96.3 KB) (pdf)
-
-
City of Bayswater Ordinary Council Reports
-
Masterplan documents
-
Pumps and Filtration EOI
-
Reports
-
Oct 2022 - Maylands Lakes Conservation Plan 2022.pdf (3.19 MB) (pdf)
-
July 2022 - Dredge closure report GHD (40.1 MB) (pdf)
-
Jan 2022 - Maylands Lakes Dredging Community Information Session (1.29 MB) (pdf)
-
Feb 2021 - Maylands Lakes Destratification 3D modelling report - GHD (2.64 MB) (pdf)
-
Dec 2020 - Proposed Actions Maylands Lakes (14 KB) (docx)
-
Sept 2020 - Maylands Lakes Management Options Assessment Report - GHD (6.71 MB) (pdf)
-
Oct 2019 - Lake Bungana sediment sampling and assessment (3.47 MB) (pdf)
-
Oct 2018 - Maylands Lakes Sediment Assessment (29.3 MB) (pdf)
-
Aug 2016 - Maylands Lakes Stage 2 Management Options Report - Essential Environmental (4.24 MB) (pdf)
-
-
Water Quality Reports
-
12665156_RPT_Maylands Lakes Quarterly Monitoring Report_Sept2025.pdf (4.75 MB) (pdf)
-
12665156_Maylands Lakes Quarterly Monitoring Report_2025-03.pdf (4.64 MB) (pdf)
-
12665156_Maylands Lakes Quarterly Monitoring Report_2025-06.pdf (6.02 MB) (pdf)
-
12622313_Maylands Lakes Monthly Monitoring Report_2025-02.pdf (2.81 MB) (pdf)
-
12622313_Maylands Lakes Monthly Monitoring Report_2025-01.pdf (3.3 MB) (pdf)
-
12622313_Maylands Lakes Monthly Monitoring Report_2024-11.pdf (4.62 MB) (pdf)
-
12622313_Maylands Lakes Monthly Monitoring Report_2024-10.pdf (2.82 MB) (pdf)
-
12622313_Maylands Lakes Quarterly Monitoring Report_2024-09.pdf (3.34 MB) (pdf)
-
12622313_Maylands Lakes Monthly Monitoring Report_2024-06.pdf (4.11 MB) (pdf)
-
Maylands Lakes Monthly Monitoring Report May 2024.pdf (4.45 MB) (pdf)
-
Maylands Lakes Monthly Monitoring Report April 2024 (2.91 MB) (pdf)
-
12622313_Maylands Lakes Monthly Monitoring Report March 2024.pdf (4.43 MB) (pdf)
-
12622313-LET_Maylands Lakes Monthly Monitoring Report February 2024.pdf (4.65 MB) (pdf)
-
12622313-LET_Maylands Lakes Monthly Monitoring Report January 2024.pdf (4.17 MB) (pdf)
-
Dec 2023 - Maylands Lakes - Interim Results Report 2022_23 (12.8 MB) (pdf)
-
Sept 2022 - Maylands Lakes - Summer 2020_21 to Winter 2022 Monitoring Report (3.16 MB) (pdf)
-
Sept 2020 - Maylands Lakes - 2019-20 Monitoring Report (71.1 MB) (pdf)
-
-
Letters to Community
Photos
Who's Listening
-
Email mail@bayswater.wa.gov.au